CIOB Managing Temporary Works Technical Information Sheet
Contents |
Summary
Most construction work requires some form of Temporary Works (to support excavations, to support concrete whilst it gains strength, to support tower cranes, etc.). These temporary works can represent a significant part of the construction processand can have a large impact on cost (sometimes 50% or more), time, quality and safety and as such, need to be properly managed to improve project delivery.
A comprehensive list of further information is included for those interested in learning more on specific aspects of temporary works.
Contents
- What are temporary works?
- How temporary works are managed
- The key parties involved
- The management controls
- How the TWC manages temporary works
- Further information on temporary works
About the author
Dr Mike Webster is Director of MPW R&R Ltd, specialising in CDM, construction and structural safety and provides consulting, forensic and expert witness services in those areas is a chartered engineer with over 30 years’ experience.
He is a member of the Temporary Works Forum, the Institution of Structural Engineers Health and Safety Panel, Structural-Safety and CROSS (the Panel for Confidential Reporting on Structural Safety).
Mike has led independent evaluations of CDM 1994 and CDM 2007 and, in 2021, was appointed by HSE to lead a review of the CDM 2015 Principal Designer role which should be published in 2021.
The Chartered Institute of Building is at the heart of a management career in construction. It is the world’s largest and most influential professional body for construction management and leadership, with a Royal Charter to promote the science and practice of building and construction for the benefit of society. With over 48,000 members worldwide, the CIOB is the international voice of the building professional.
Visit the CIOB Academy technical publications page for purchase link: https://www.ciobacademy.org/product/managing-temporary-works/
Available now.
CIOB Academy Technical Information Sheets are short documents that give a technical overview on a variety of themes, CIOB members can access Technical Information Sheets for FREE and receive a 20% discount on our Codes and Guides. Your discount codes are in the member's portal. If you experience difficulties accessing the portal, contact CIOB.
--CIOB
- Cofferdam.
- Crane supports.
- Debris netting.
- Design and Check Certificates.
- Excavating plant.
- Facade retention.
- Falsework.
- Formwork.
- Groundworks.
- Ground anchor.
- Hesco barrier.
- PAS 8811:2017 Temporary works.
- Scaffolding.
- Shoring.
- Temporary works for construction
- The design of temporary structures and wind adjacent to tall buildings.
- Trench support.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Construction Management, 8 July
NEETs crisis drives interest in trades, but apprenticeships barriers remain.
Passive fire protection webinar
MEP services penetration seals.
Where its at podcast (and video) - The role of the Architectural Technologist as an Expert Witness.
More than 200 remarkable buildings added to SAVE’s Buildings at Risk register.
Government scraps pre-application consultation for Nationally Significant Infrastructure Projects.
Historic England and infrastructure
New projects offer opportunities for the historic environment and local communities.
Construction Management, 2 July
Construction deaths halve in two years.
Green Book changes to drive investment in all parts of UK.
Minimum energy efficiency standards (MEES)
CIAT briefing on response to consultations for privately rented non-domestic properties.
Connect, collaborate, shape the future
Registration now live for UK Construction Week Birmingham.
CIOB announces Saul Humphrey FCIOB as new President for 26/27 term.
A quick, simple, and zero-bills solution to prevent overheating.